High Street Watermain Replacement Project in Spring 2022
Share High Street Watermain Replacement Project in Spring 2022 on FacebookShare High Street Watermain Replacement Project in Spring 2022 on TwitterShare High Street Watermain Replacement Project in Spring 2022 on LinkedinEmail High Street Watermain Replacement Project in Spring 2022 link
The High Street Watermain Replacement Project area is located in the Bridgeburg section of Fort Erie that extends from Idylewylde Street in the north to Catherine Street in the south.
The Water Distribution System Master Plan completed in April 2017 recommended the replacement of the existing 150mm diameter Asbestos Cement watermain within the short term (0-10 years). The results of the Water Distribution System Master Plan showed that replacement of the existing watermain will have a positive effect on water quality.
The Town’s Asset Management plans risk analysis showed that this section of High Street (Approximately 250m) requires the following work:
Replacement of the existing 150mm diameter Asbestos Cement watermain with 150mm PVC watermain, including replacement the existing fire hydrants and all services up to/including curb stops at the property line.
Replacement of the existing 200mm diameter Asbestos Cement Sanitary sewer with 200mm diameter PVC Sanitary Sewer including maintenance holes and services to the property line.
Replacement of the existing 300mm diameter CSP Storm sewer with 300mm and 350mm diameter PVC Storm Sewer including the maintenance holes.
Full reconstruction of the road with shoulders.
Please review the documents included on the right-hand side of this page and complete the survey. We would like to hear your thoughts and concerns on this project prior to construction.
The High Street Watermain Replacement Project area is located in the Bridgeburg section of Fort Erie that extends from Idylewylde Street in the north to Catherine Street in the south.
The Water Distribution System Master Plan completed in April 2017 recommended the replacement of the existing 150mm diameter Asbestos Cement watermain within the short term (0-10 years). The results of the Water Distribution System Master Plan showed that replacement of the existing watermain will have a positive effect on water quality.
The Town’s Asset Management plans risk analysis showed that this section of High Street (Approximately 250m) requires the following work:
Replacement of the existing 150mm diameter Asbestos Cement watermain with 150mm PVC watermain, including replacement the existing fire hydrants and all services up to/including curb stops at the property line.
Replacement of the existing 200mm diameter Asbestos Cement Sanitary sewer with 200mm diameter PVC Sanitary Sewer including maintenance holes and services to the property line.
Replacement of the existing 300mm diameter CSP Storm sewer with 300mm and 350mm diameter PVC Storm Sewer including the maintenance holes.
Full reconstruction of the road with shoulders.
Please review the documents included on the right-hand side of this page and complete the survey. We would like to hear your thoughts and concerns on this project prior to construction.
Please take a few minutes to complete our short survey. Your feedback is important to us!
Please note that information will be collected in accordance with the Municipal Freedom of Information and Protection of Privacy Act. With the exception of personal information, please note all comments will become part of the public record.
CLOSED: This survey has concluded.
Share High Street Watermain Replacement - Resident Survey on FacebookShare High Street Watermain Replacement - Resident Survey on TwitterShare High Street Watermain Replacement - Resident Survey on LinkedinEmail High Street Watermain Replacement - Resident Survey link
Page last updated: 07 Jul 2022, 11:36 AM
Signup Banner
to get involved!
Project Timeline
Phase 1 - Engage public for feedback within project area.
High Street Watermain Replacement Project in Spring 2022 has finished this stage
Monday, November 15th, 2021 to Friday, November 26th, 2021
Phase 2 - Finalize plans based on any feedback received or issues raised.
High Street Watermain Replacement Project in Spring 2022 has finished this stage
Phase 3 - Award of Tender For High Street Watermain Replacement
High Street Watermain Replacement Project in Spring 2022 has finished this stage
Council-in-Committee meeting held on Monday, February 14, 2022
Phase 4 - Schedule construction start date for High Street Watermain Project.
High Street Watermain Replacement Project in Spring 2022 has finished this stage
Tentative construction start date is the week of April 11th, 2022.
Phase 5 - Construction Progress
High Street Watermain Replacement Project in Spring 2022 has finished this stage
100% Completion.
Watermain, Sanitary and Storm replacement has been completed. Asphalt Placement, and property restoration is completed.
Phase 6 - Construction Complete
High Street Watermain Replacement Project in Spring 2022 is currently at this stage
Project reached substantial completion in August 2022.