Public Consultation for Ott Road and West Main Street Upgrade
Share Public Consultation for Ott Road and West Main Street Upgrade on FacebookShare Public Consultation for Ott Road and West Main Street Upgrade on TwitterShare Public Consultation for Ott Road and West Main Street Upgrade on LinkedinEmail Public Consultation for Ott Road and West Main Street Upgrade link
The Ott Road and West Main Street Upgrade Project area is located in urban community of Stevensville section of Fort Erie. The project area is located along Ott Road from the CN Railway tracks to West Main Street and West Main Street from Ott Road to May Avenue.
The timing of the project is driven by the Village Creek Estates development located south of West Main Street. A risk analysis of this area was also conducted through the Town's Asset Management Plan.
The results of the risk analysis recommended the replacement of approximately 300m of 150mm diameter cast iron watermain along Ott Road from North of the CN Railway Tracks to West Main Street.
The Ott Road and West Main Street upgrade was also identified in the 2018 Development Charges Background Study.
The general scope of work for this project includes full reconstruction and upgrade of the existing Ott Road and West Main Street roadway section to an urban cross-section including installation of storm sewer infrastructure, new sidewalks and concrete curb and gutter. In addition, replacement of the existing 150mm diameter cast iron watermain along Ott Road from North of the CN Railway Tracks to West Main Street.
Virtual Public Consultation
This online public consultation provides residents with the opportunity to review the associated documents relating to the project and provide feedback on this project prior to construction.
Please review the documents included on the right hand side of this page and complete the survey. We would like to hear your thoughts and concerns on this project prior to construction.
A question submission period will open from Monday, July 22, 2024 to Friday, August 9, 2024.
The Ott Road and West Main Street Upgrade Project area is located in urban community of Stevensville section of Fort Erie. The project area is located along Ott Road from the CN Railway tracks to West Main Street and West Main Street from Ott Road to May Avenue.
The timing of the project is driven by the Village Creek Estates development located south of West Main Street. A risk analysis of this area was also conducted through the Town's Asset Management Plan.
The results of the risk analysis recommended the replacement of approximately 300m of 150mm diameter cast iron watermain along Ott Road from North of the CN Railway Tracks to West Main Street.
The Ott Road and West Main Street upgrade was also identified in the 2018 Development Charges Background Study.
The general scope of work for this project includes full reconstruction and upgrade of the existing Ott Road and West Main Street roadway section to an urban cross-section including installation of storm sewer infrastructure, new sidewalks and concrete curb and gutter. In addition, replacement of the existing 150mm diameter cast iron watermain along Ott Road from North of the CN Railway Tracks to West Main Street.
Virtual Public Consultation
This online public consultation provides residents with the opportunity to review the associated documents relating to the project and provide feedback on this project prior to construction.
Please review the documents included on the right hand side of this page and complete the survey. We would like to hear your thoughts and concerns on this project prior to construction.
A question submission period will open from Monday, July 22, 2024 to Friday, August 9, 2024.
Page last updated: 12 Aug 2024, 11:15 AM
Signup Banner
to get involved!
Project Timeline
Open
Public Consultation for Ott Road and West Main Street Upgrade is currently at this stage
This consultation is open for contributions.
Under Review
this is an upcoming stage for Public Consultation for Ott Road and West Main Street Upgrade
Contributions to this consultation are closed for evaluation and review. The project team will report back on key outcomes.
Final report
this is an upcoming stage for Public Consultation for Ott Road and West Main Street Upgrade
The final outcomes of the consultation are documented here. This may include a summary of all contributions collected as well as recommendations for future action.