Bridge & Culvert Repair/Replacement Program (BRIG22/BRIG21) in November and December, 2021

Share Bridge & Culvert Repair/Replacement Program (BRIG22/BRIG21) in November and December, 2021 on Facebook Share Bridge & Culvert Repair/Replacement Program (BRIG22/BRIG21) in November and December, 2021 on Twitter Share Bridge & Culvert Repair/Replacement Program (BRIG22/BRIG21) in November and December, 2021 on Linkedin Email Bridge & Culvert Repair/Replacement Program (BRIG22/BRIG21) in November and December, 2021 link

Nigh Road Culvert (S077B) Rehabilitation between Centralia Avenue and Stonemill Road.

There are available detour routes so construction will proceed with Nigh Road closed between 0700 and 1700 for the duration of the work. The detour roads are Stonemill Road, Highway #3, and Centralia Avenue.

Construction is expected to occur November 2, 2021 to November 5, 2021. The rehabilitation work will include installation of scour protection through the structure.


Friendship Trail Culvert (S110B) Rehabilitation between Crescent Road and Kraft Road.

It is expected the trail will be open with occasional short duration closures for specific contractor activities. Users may experience some delays.

Construction is expected to occur November 2, 2021 to November 5, 2021. The rehabilitation work will include installation of slope stability works.


Miller Avenue Culvert (S066B) Rehabilitation between Cairn’s Crescent and Bowen Road.

There are available detour routes so construction will proceed with Miller Avenue closed for the duration of the project. The detour roads are Bowen Road, Pettit Road, and Cairn’s Crescent.

Construction is expected to start November 8, 2021 to November 16, 2021. The rehabilitation work will include installation of slope stability and scour protection works at each end of the structure.


Pettit Road Culvert (S069B) Rehabilitation between Cairn’s Crescent and Bowen Road.

There are available detour routes so construction will proceed with Pettit Road closed for the duration of the project. The detour roads are Bowen Road, Sunset Drive, and Cairn’s Crescent.

Construction is expected to start November 4, 2021 to November 12, 2021. The rehabilitation work will include installation of slope stability and scour protection works at each end of the structure.


Pettit Road Culvert (M307C) Replacement between Bridge Street and Bowen Road.

There are available detour routes so construction will proceed with Pettit Road closed for the duration of the project. The detour roads are Bowen Road, Thompson Road, and Gilmore Road.

Construction is expected to occur November 24, 2021 to December 17, 2021. The new culvert will be a twin HDPE 1200mm diameter round culvert.


Point Abino Culvert (M302C) Replacement between Point Abino Road and Netherby Road.

There are available detour routes so construction will proceed with Point Abino Road closed for the duration of the project. The detour roads are Stevensville Road and Netherby Road.

Construction is expected to start November 29, 2021 to December 10, 2021. The new culvert will be a twin HDPE 1200mm diameter round culvert.



Nigh Road Culvert (S077B) Rehabilitation between Centralia Avenue and Stonemill Road.

There are available detour routes so construction will proceed with Nigh Road closed between 0700 and 1700 for the duration of the work. The detour roads are Stonemill Road, Highway #3, and Centralia Avenue.

Construction is expected to occur November 2, 2021 to November 5, 2021. The rehabilitation work will include installation of scour protection through the structure.


Friendship Trail Culvert (S110B) Rehabilitation between Crescent Road and Kraft Road.

It is expected the trail will be open with occasional short duration closures for specific contractor activities. Users may experience some delays.

Construction is expected to occur November 2, 2021 to November 5, 2021. The rehabilitation work will include installation of slope stability works.


Miller Avenue Culvert (S066B) Rehabilitation between Cairn’s Crescent and Bowen Road.

There are available detour routes so construction will proceed with Miller Avenue closed for the duration of the project. The detour roads are Bowen Road, Pettit Road, and Cairn’s Crescent.

Construction is expected to start November 8, 2021 to November 16, 2021. The rehabilitation work will include installation of slope stability and scour protection works at each end of the structure.


Pettit Road Culvert (S069B) Rehabilitation between Cairn’s Crescent and Bowen Road.

There are available detour routes so construction will proceed with Pettit Road closed for the duration of the project. The detour roads are Bowen Road, Sunset Drive, and Cairn’s Crescent.

Construction is expected to start November 4, 2021 to November 12, 2021. The rehabilitation work will include installation of slope stability and scour protection works at each end of the structure.


Pettit Road Culvert (M307C) Replacement between Bridge Street and Bowen Road.

There are available detour routes so construction will proceed with Pettit Road closed for the duration of the project. The detour roads are Bowen Road, Thompson Road, and Gilmore Road.

Construction is expected to occur November 24, 2021 to December 17, 2021. The new culvert will be a twin HDPE 1200mm diameter round culvert.


Point Abino Culvert (M302C) Replacement between Point Abino Road and Netherby Road.

There are available detour routes so construction will proceed with Point Abino Road closed for the duration of the project. The detour roads are Stevensville Road and Netherby Road.

Construction is expected to start November 29, 2021 to December 10, 2021. The new culvert will be a twin HDPE 1200mm diameter round culvert.



  • Municipal Class Environment Assessment

    Share Municipal Class Environment Assessment on Facebook Share Municipal Class Environment Assessment on Twitter Share Municipal Class Environment Assessment on Linkedin Email Municipal Class Environment Assessment link

    The following document provides an overview of results collected from a recent assessment of Winger Road Bridge. The study also includes preliminary recommendations.

    A question submission period will be open until August 22, 2021.

Page last updated: 03 Dec 2021, 02:58 PM