November 2023 → April 2024
Environmental Assessment - Phase 1
- Background review
- Technical studies and inventories
- Hydrology and hydraulics analysis
- Public Meeting
May → September 2024
Environmental Assessment - Phase 2
- Develop a long-list of alternatives
- Establish an evaluation methodology and criteria
- Short-list the alternatives list
- Select a preliminary preferred solution
- Public meeting
- Project File Report
November 2024 → October 2025
Anticipated Timeline for Detailed Design